News Release: from the Katy Freeway Public Information Office
SH 99 Under I-10 Mainlanes Now Open
Thursday, Mar 3rd, 2005
Balfour Beatty Construction successfully completed their milestone to restore cross corridor traffic at SH 99 effective as of 1PM today, March 3. The SH 99 bridge over I-10 was taken out of service on February 16th and the contractor had a total of 37 days in which to re-store north/south travel at SH 99. In just over half the allocated time, the contractor has completed the construction of the new I-10 mainlane bridge over SH 99 and the new SH 99 southbound frontage road. Consequently, the contractor will collect the maximum incentive of $500, 0000. SH 99 northbound and southbound traffic is now placed on the new southbound frontage road until the contractor completes the new SH 99 northbound frontage.