News Release: from the Katy Freeway Public Information Office
Upcoming Katy Freeway Program Closures
Friday, Jul 21st, 2006
Below is a list of the upcoming closures associated with the Katy Freeway Reconstruction Program as of July 21, 2006.
CONTRACTS E1 & E2 (BETWEEN BELTWAY 8 and I-610) CLOSURES
• There will be a TOTAL CLOSURE of GESSNER at I-10/KATY FREEWAY on Saturday, July 22 from 5:00 AM to 6:00 PM. Detour to the westbound frontage road to Beltway 8, go through the intersection to the eastbound frontage road to Gessner.
• One inside lane of I-10/KATY FREEWAY eastbound from BELTWAY 8-WEST to BUNKER HILL RD will be closed on Saturday, July 22 from 5:00 AM to 6:00 PM.
CONTRACT F (I-10/ I-610 IINTERCHANGE) CLOSURES
• The I-10/KATY FREEWAY eastbound and westbound direct connector ramps to I-610/WEST LOOP southbound will be closed on Saturday, July 22 from 6:00 AM to 9:00 PM. Detour to IH 610 northbound to W. 18th and u-turn to IH 610 southbound.
*****************************************************************************
A Glimpse At Next Weekend's Work...
CONTRACT E1 & E2 (BETWEEN BELTWAY 8 and I-610) CLOSURES
• Saturday, July 29 Williams Brothers Construction will switch traffic onto the new i-10/KATY FREEWAY westbound frontage road between ANTOINE and west of BINGLE/VOSS. As a result, three I-10 westbound ramps including the Antoine entrance ramp, the Wirt exit ramp and the Bingle/Voss exit ramp will be closed until February 2007 while WB completes construction of the new I-10 westbound mainlanes in the area. A detailed map and detours will be released in the upcoming week.
Please note that all closures are subject to change due to inclement weather. For more information on the Katy Freeway Reconstruction Program including up to date information regarding other lane closures along the I-10 corridor, please visit the Katy Freeway website at www.katyfreeway.org or contact the Katy Freeway Public Information Office at 281-589-5924.