Upcoming Katy Freeway Program Closures

Friday, Aug 3rd, 2007

Below is an updated list of the scheduled closures associated with the Katy Freeway Reconstruction Program as of Friday, August 3, 2007.

CONTRACT C1 (SH 6 to east of ELDRIDGE) CLOSURES
. Two lanes of the I-10/KATY FREEWAY eastbound mainlanes between SH-6 and ELDRIDGE will be closed beginning 8 PM, Friday, August 3 until 5 AM, Saturday, August 4 as contractors transition the existing I-10 eastbound mainlane traffic onto new pavement.

. The I-10/KATY FREEWAY eastbound entrance ramp from PARK TEN will be closed effective 9 PM, Friday, August 3 until further notice. Motorists will now access I-10 eastbound via the entrance ramp from SH-6.

. The I-10/KATY FREEWAY eastbound exit ramp to ELDRIDGE will be closed beginning 9 PM, Friday, August 3 until 5 AM, Monday, August 6.

. There will be alternating lanes closed on the I-10/KATY FREEWAY eastbound frontage road between SH-6 and ELDRIDGE beginning 5 AM, Saturday, August 4 until 5 AM, Sunday, August 5.

. There will be a TOTAL CLOSURE of northbound and southbound SH-6 at I-10/KATY FREEWAY overnight beginning 10 PM, Saturday August 4 until 6 AM, Sunday, August 5. Northbound traffic will detour east on the I-10 eastbound frontage road to Eldridge, u-turn to the I-10 westbound frontage road to access SH-6, southbound traffic will detour west on the I-10 westbound frontage road to Park Ten, u-turn to the I-10 eastbound frontage road to access SH-6.

CONTRACT C2 (DAIRY ASHFORD to east of KIRKWOOD) CLOSURES
. There will be alternating lanes closed on northbound and southbound DAIRY ASHFORD at I-10/KATY FREEWAY on Saturday, August 4 from 7 AM to 3 PM as traffic is switched to new pavement.

. There will be alternating lanes closed on northbound and southbound KIRKWOOD at I-10/KATY FREEWAY on Sunday, August 5 from 7 AM to 3 PM as traffic is switched to new pavement.

. There will be a alternating lanes closed on northbound and southbound KIRKWOOD at I-10/KATY FREEWAY on Monday, August 6 from 9 AM to 3 PM.

. The left lane of the I-10/KATY FREEWAY westbound frontage road between KIRKWOOD and DAIRY ASHFORD, will be closed on Monday, August 6 from 9 AM to 3 PM.

CONTRACT D (I-10/BELTWAY 8 INTERCHANGE) CLOSURES
. There will be a TOTAL CLOSURE of the I-10/KATY FREEWAY eastbound mainlanes between WILCREST and GESSNER beginning 5 AM, Saturday, August 4 until 5 AM, Monday, August 6. Traffic will detour at the Beltway 8 frontage road exit to the I-10 eastbound frontage road and re-enter the I-10 eastbound mainlanes just west of Gessner.

. There will be a TOTAL CLOSURE of the I-10/KATY FREEWAY westbound direct connector ramp to southbound BELTWAY 8-WEST from 5 AM, Saturday, August 4 until 5 AM, Monday, August 6. Southbound traffic should take the Beltway 8 frontage road exit to the I-10 westbound frontage road.

. There will be a TOTAL CLOSURE of the BELTWAY 8-WEST northbound frontage road between QUEENSBURY and I-10/KATY FREEWAY and the Beltway 8-West northbound frontage road flyover bridge from 5 AM, Saturday, August 4 until 5 AM, Monday, August 6. Traffic will detour east on Queensbury to Town and Country, north on Attingham to the I-10 eastbound frontage road.

. There will be a TOTAL CLOSURE of the BELTWAY 8-WEST southbound frontage road at I-10/KATY FREEWAY from 5 AM, Saturday, August 4 until 5 AM, Monday, August 6. Southbound traffic will detour to the Beltway 8-West southbound frontage road flyover bridge.

. There will be nightly alternate lane closures on the BELTWAY 8-WEST southbound mainlanes from Westview over to Memorial from 10 PM to 5 AM, Monday, August 6 – Tuesday, August 7.

. There will be nightly alternate lane closures on the BELTWAY 8-WEST northbound mainlanes from Memorial to Westview from 10 PM to 5 AM on Wednesday, August 8 – Thursday, August 9.

CONTRACTS E1 & E2 (BETWEEN BELTWAY 8 and I-610) CLOSURES
. There will be a TOTAL CLOSURE of northbound and southbound BLALOCK/ECHO LANE north of the I-10/KATY FREEWAY westbound frontage road from 9 PM, Friday, August 3 until 6 PM, Sunday, August 5. Northbound traffic will detour east on the I-10 eastbound frontage road to Campbell, go through the intersection to the I-10 westbound frontage road to Blalock; southbound traffic will detour west on Westview, south on Bunker Hill to the I-10 eastbound frontage road, to Echo.

. There will be a TOTAL CLOSURE of northbound and southbound ANTOINE at I-10/KATY FREEWAY on Saturday, August 4 from 7 AM to 9 PM. Northbound traffic will detour east on the I-10 eastbound frontage road to Silber, go through the intersection to the I-10 westbound frontage road to Antoine; southbound traffic will detour west on the I-10 westbound frontage road, south on Chimney Rock/Wirt to the I-10 eastbound frontage road, to Antoine.

. The left lane of the I-10/KATY FREEWAY eastbound mainlanes from just west of CHIMNEY ROCK to ANTOINE and the I-10/KATY FREEWAY eastbound entrance ramp from CHIMNEY ROCK will be closed Saturday, August 4 from 7 AM to 9 PM.

. One inside lane of northbound CHIMNEY ROCK between the I-10/KATY FREEWAY eastbound frontage road and HICKORY SHADOWS will be closed until 6 PM, Sunday, August 5.

. The right turn lane of the I-10/KATY FREEWAY westbound frontage road at CHIMNEY ROCK/WIRT will be closed until 5 AM, Monday, August 6.



CONTRACT G (I-610 to west of WASHINGTON) CLOSURES
. The outside of the lane of I-10/KATY FREEWAY will be closed between I-610/WEST LOOP to WASHINGTON AVE/WESTCOTT ST. nightly from 9 PM to 5 AM from Monday, August 6 to Thursday, August 9.

****************************************************************************


Please note that all closures are subject to change in the event of inclement weather. For more information on the Katy Freeway Reconstruction Program including up to date information regarding other lane closures along the I-10 corridor, please visit the Katy Freeway website at www.katyfreeway.org or contact the Katy Freeway Public Information Office at 281-589-5924.
Check out the weekly forecast of upcoming closures associated with the Beltway 8/I-10 Katy Freeway direct connectors on our web site http://www.katyfreeway.org/Beltway8/Weekly_Forecast.html.



Powered by NewsRouter.com